Works are nearing completion on the Weatherald
Terrace section of the project. This work included:
- extension of the shared use path along the foreshore as part of the
State Government’s Coast Park project.
- 400m of retaining and reinforcement work along Weatherald Terrace
to prevent further erosion
- a new boardwalk and stairs to the South Port Bridge
- road realignment
- reconfiguration of ramps around the existing Weatherald Terrace
toilet block to make them compliant with the Disability Act.
Following a period of closure
Weatherald Terrace was reopened for through traffic on 24 November 2018.
Safety
The design includes a 185 metre
section where fencing is provided on both sides of the path. This long, steep
section of path creates a potential for higher speeds by cyclists which
increase the likelihood of an accident occurring. The section also includes a safety
barrier for cars which is required due to the risk associated with the steep
road, the location of the cliff and the curve of the road. The new safety
barrier replaces the barrier that was previously located on the edge of the cliff.
With the potential higher speeds and the significant consequences of having a
cliff on one side and the safety barrier on the other, having protection for
cyclists on both sides was considered necessary in order to meet Council’s
obligations under the Work Health and Safety Act.
Share on Facebook
Share on Linkedin
Email this link
Works are nearing completion on the
Trafalgar and Wembley Street carparks with only minor works to be completed in
these areas. Both of these carparks have been re-opened to the public. The Nelson
Street carpark work is continuing with these work expected to be completed in early
December. The works in the Nelson Street Carpark include:
- construction of a 3m wide shared path
- reconfiguration of the existing car park area to accommodate the
new path
- replacement of the existing shelter and installation of new shelters
and seating areas
- upgraded landscaping including seating and BBQ
- new coastal fencing.
The Wembley Street carpark and public toilet have now been re-opened for use. The Nelson Street carpark is scheduled to be re-opened by the end of November. Landscape works in the central portion may be still ongoing beyond thus but are aimed at being substantially complete by the end of the year.
Share on Facebook
Share on Linkedin
Email this link
The
Nelson Street Carpark is scheduled to be reopened by the end of November.
Landscape works in the central portion may be still ongoing beyond this but are
aimed at being substantially complete by the end of the year.
Share on Facebook
Share on Linkedin
Email this link
Works on the section of Saltfleet Street between the bridge and Commercial Road are now underway. These works include:
- narrowing of the road to accommodate new 3m wide shared path
- improvement to the pedestrian crossing points to Jubilee Park
- improvement to the northern vehicle access to Jubilee Park
- improvements to the bus stops near Jubilee Park
- new line marking including extending the bike lane on the eastern side of the road.
During the work on Saltfleet Street:
- speed reductions will in place
- protective barriers and bollards will be used to direct traffic and protect the workers on site
- pedestrians will be diverted to use the eastern side of the road
- the northern access to the Jubilee playground will be temporarily restricted to left-in and left-out movements only. There will be no change to the southern entry to the playground.
It is expected that these works will be completed by the end of the year.