March/April Update

about 1 year ago

The Douglas Gully road widening is still progressing well, however is now expected to be completed by May/June.

With a Vintage and the number of businesses in the area, we wanted to ensure continued business as usual without any major disruptions due to the road works.

To do this, we've had to work in sections, rather than closing the road to complete it faster. This has enabled two way traffic for the majority of the works so far.

Whilst this means a longer than anticipated project length, we hope the community have encountered less disruptions with no detours.

Every effort will continue to be taken to keep two way traffic in place and at times one way traffic with traffic lights.

The road widening is progressing, however the extreme hot weather may cause delays to the completion date. We will continue to keep the community informed as work progresses.

Every effort will be taken to keep two way traffic in place, however at some stages of the work, one way traffic will be required with traffic lights in place.