Intersection Upgrades - Sunnymeade Drive Aberfoyle Park

LATEST UPDATE

Work is continuing to upgrade the intersections of Sunnymeade Drive/Hub Drive and Sunnymeade Drive/Campus Drive.

There have been some unexpected delays during February and March associated with the relocation and alteration of existing services.

We now estimate completion of the project to be around mid April 2020.

Every effort will be made to reduce impacts to the community and we will continue to update this page and use on site signage to notify commuters of changes to traffic conditions.



The upgrades will consist of:

  • New left and right turning lanes at the intersections of Sunnymeade Drive/Hub Drive and Sunnymeade Drive/Campus Drive.
  • Realigning new curbs and footpaths
  • Widening the road
  • Installation of new lighting and removing the old
  • Upgrading the existing crossing to a pedestrian activated crossing
  • Relocating bus stop 48
  • Removing some trees/shrubs to allow for road widening (new trees/shrubs will be planted)
  • Trimming of existing trees/shrubs where required

For more detailed information and to view the new design, please see the document library.


LATEST UPDATE

Work is continuing to upgrade the intersections of Sunnymeade Drive/Hub Drive and Sunnymeade Drive/Campus Drive.

There have been some unexpected delays during February and March associated with the relocation and alteration of existing services.

We now estimate completion of the project to be around mid April 2020.

Every effort will be made to reduce impacts to the community and we will continue to update this page and use on site signage to notify commuters of changes to traffic conditions.



The upgrades will consist of:

  • New left and right turning lanes at the intersections of Sunnymeade Drive/Hub Drive and Sunnymeade Drive/Campus Drive.
  • Realigning new curbs and footpaths
  • Widening the road
  • Installation of new lighting and removing the old
  • Upgrading the existing crossing to a pedestrian activated crossing
  • Relocating bus stop 48
  • Removing some trees/shrubs to allow for road widening (new trees/shrubs will be planted)
  • Trimming of existing trees/shrubs where required

For more detailed information and to view the new design, please see the document library.


We may need to gather information to answer your query, but will endevour to reply within 48 hours.

Please note, that we monitor questions during workings hours only, Monday to Fridays. 