Road Reconstruction and Upgrade - Justs Road Aldinga Beach/Sellicks Beach


JANUARY UPDATE

Stage 1 work (Norman Road to Button Road) was completed in December 2019 and we are commencing preparation work for Stage 2.

Stage 2 works commenced on 20 January 2020 and are schedule for completion by August 2020, subject to favourable weather conditions.

Justs Road Stage 2 is from Button Road to Sellicks Beach Road. Early works are focused on the drainage swales on the road shoulders on each side of the road.

Through early February, SA Water contractors will also be on site working on relocating a segment of the water main to accommodate new drainage infrastructure being installed as part of the road reconstruction.

Stay tuned for our next update here.

STAGES OF WORK

Stage One, from Norman Rd to Button Rd consists of:

  • Widening the existing traffic lanes to 3.5m in each direction with new pavement installed.
  • Modifying driveways with shallow culverts underneath for stormwater.
  • Realigning the grassed drainage swales on both sides of the road.
  • Guard rail installations at selected locations.
  • Widening the road shoulders to improve the bus waiting area at bus stop 131 on both the east and west sides.

Stage Two

Stage two consists of the section of Justs Road from Button Road to Sellicks Beach Road (excludes the Sellicks Beach Road intersection).




JANUARY UPDATE

Stage 1 work (Norman Road to Button Road) was completed in December 2019 and we are commencing preparation work for Stage 2.

Stage 2 works commenced on 20 January 2020 and are schedule for completion by August 2020, subject to favourable weather conditions.

Justs Road Stage 2 is from Button Road to Sellicks Beach Road. Early works are focused on the drainage swales on the road shoulders on each side of the road.

Through early February, SA Water contractors will also be on site working on relocating a segment of the water main to accommodate new drainage infrastructure being installed as part of the road reconstruction.

Stay tuned for our next update here.

STAGES OF WORK

Stage One, from Norman Rd to Button Rd consists of:

  • Widening the existing traffic lanes to 3.5m in each direction with new pavement installed.
  • Modifying driveways with shallow culverts underneath for stormwater.
  • Realigning the grassed drainage swales on both sides of the road.
  • Guard rail installations at selected locations.
  • Widening the road shoulders to improve the bus waiting area at bus stop 131 on both the east and west sides.

Stage Two

Stage two consists of the section of Justs Road from Button Road to Sellicks Beach Road (excludes the Sellicks Beach Road intersection).



  • October Update

    2 months ago
    Oct image 3

    Work progressed well and we were on track to complete Stage 1 (section between Norman Rd and Button Rd) by the end of this year, weather permitting.

    So far we have:

    • Reconstructed failed sections of pavement
    • Widened the road
    • Formalised and widened drainage swales on both sides of the road
    • Resealed and line-marked completed sections

    Over the next month we will be concentrating on:

    • Finishing the current section of road
    • Commencing work at the Button Road intersection
    • Installing road safety barriers at the Button Road intersection and around the culvert crossing south of Norman Road.

    You may have noticed that...

    Work progressed well and we were on track to complete Stage 1 (section between Norman Rd and Button Rd) by the end of this year, weather permitting.

    So far we have:

    • Reconstructed failed sections of pavement
    • Widened the road
    • Formalised and widened drainage swales on both sides of the road
    • Resealed and line-marked completed sections

    Over the next month we will be concentrating on:

    • Finishing the current section of road
    • Commencing work at the Button Road intersection
    • Installing road safety barriers at the Button Road intersection and around the culvert crossing south of Norman Road.

    You may have noticed that the road pavement is being reconstructed in sections. This is to allow us to keep the road operational during the works.


  • September 2019 Update

    4 months ago

    To reduce community impacts, the construction methodology for Stage 1 of Justs Road was changed from a full road closure to a part road closure.

    This has meant that work to reconstruct this section will be extended until the end of the year.


    To reduce community impacts, the construction methodology for Stage 1 of Justs Road was changed from a full road closure to a part road closure.

    This has meant that work to reconstruct this section will be extended until the end of the year.