March Update 2020

3 months ago

Through March, profiling works were undertaken and the road pavement is now nearly complete for the 500m rural road segment from Button Road. We will finish this segment and have the road spray-sealed before the Easter break.

Works have continued on the main drainage pipe-run beyond the rural segment into the urban road area with the pipe run now approaching Tangier Boulevard.

Over the next month efforts will be focused on continuing the pipe run up Beyond Monaco Blvd and constructing the new bus stops on the eastern side of the road before we can commence the new kerb construction.

The road will continue to be open for traffic through this period with some further changing restrictions applied as required.