Project update April 2025 - final design
The design has been finalised for the Forsyth Reserve hard courts and can be viewed here.
Some small changes have been made to the design to suit the layout and maintain the budget. These include:
- asphalt mound and undulation on the bike track replaced with speed humps
- additional pavement games added
- creek connection and planting removed.
The netball hoops have already been installed as part of the work undertaken in 2024.
Construction for this project is scheduled to take place during the 2025-26 financial year.