This project is not open for feedback. We’re simply informing the community about the upcoming works.

As part of our 2025-26 Project and Capital Works Program, we are proposing the renewal of the existing car park at Lower Esplanade, Aldinga Beach, next to the Pearl Restaurant.

Car park renewal works include:

  • Renewal of the carpark asphalt surface to address deterioration and extend its useful life.
  • Fresh linemarking with some minor modifications to improve parking functionality and flow.
  • Adjusting the allocation of disabled permit parking spots from four to three to better align with community needs and usage patterns.
  • Replacement of defective kerbing on the southern side of the car park to enhance safety and aesthetics.
  • Installation of bicycle locking stations to support sustainable transport options.

During the works:

  • The boat ramp will remain fully operational.
  • Toilets will stay open but may be harder to access.

A cultural heritage assessment has been undertaken, and no foreseeable impacts have been identified.

Please download a copy of the concept plan illustrating the proposed works under the documents area on this webpage.

The works are proposed to commence in July with completion expected end of September, subject to weather and external factors.

Lower car park Aldinga Beach

For full details of all works proposed for Lower car park Aldinga Beach, please see the concept plan.