Work is nearly complete

4 March 2025

Work commenced in January and progress is 90% complete.

So far, we have completed:

  • Expanded building structure
  • First fix of services
  • Lift installation
  • External site works including extended carpark, lighting, paths

Work continues on the second fix of services and internal fit out.

Anticipated building completion is March 2025.

View the construction progress photos here