We are upgrading the section of Old Coach Road between and including Oleander Road and Tuit Road, Maslin Beach.

Construction is scheduled to commence mid-February and to be completed late June 2024.

Scope of works include:

  • reconstruction of the road between Oleander Road and Tuit Road
  • installation of stormwater infrastructure
  • minor road widening in nominated locations
  • vehicle safety improvements including line marking, indented bus bays and guardrails.

You can view the concept plan for more detail.

Traffic restrictions and road closures

Traffic restrictions will be in place for the duration of works, with complete road closures and detours required at critical stages during construction. Buses will be exempt and bus services will operate as normal. Road closures are scheduled between February and April 2024 and advance notice of the closures will be provided by variable message signs (VMS) prior to the closure commencing. Outside of the road closures, we will endeavor to maintain traffic flows through the worksite.

To avoid traffic delays while works are underway, it is recommended to use an alternate route via Main South Road which will be open to through traffic during construction.

The majority of works on Old Coach Road are scheduled to commence after the completion of the Tour Down Under event.