May Update

about 1 month ago

Work is progressing well on Stage two (Button Road to Sellicks Beach Road) and we are on track for completion by August 2020, subject to favourable weather conditions.

At Justs Road the first 500m of road construction south of Norman Road was sealed the week before the Easter Break. Speed restrictions are still in place while the seal settles and we finalise driveways and swale works along this segment of road.

Beyond the rural road segment we have now completed the 500m stormwater drain as part of the Urban Section of Road approaching Sellicks Beach Road. Culverts have been installed in preparation for the new concrete bus pads and kerbing works have commenced.

Through May we will be recommencing profiling to continue concrete and kerbing works and commence construction of the new 1.5m wide footpath along the western edge of road.

Throughout May the road will continue to be open for traffic with some further changing restrictions applied as required.