News

August 2023

30 August 2023

Upgrade works are continuing to progress. Since the July update:

  • picnic shelters with tables and bench seats have been installed
  • football posts have been installed
  • concrete pitches for the cricket nets have been poured, with the nets to be installed in the coming month
  • playground shade sail posts have been installed, with the shade sail to be installed in the next couple of weeks.

The dog waste bag dispenser has also been moved from the stand near Candy Road to another post directly adjacent to the rubble carpark area.

Application of an acrylic layer and line marking on the basketball court is scheduled for October and will mark completion of the reserve upgrade.