Nature Playspace - Wilfred Taylor Reserve

NATURE PLAYSPACE CONSTRUCTION UNDERWAY

It's full steam ahead for the State Government and Council funded nature playspace at the Wilfred Taylor Reserve in Morphett Vale scheduled to be open in mid-2020.

HAPPENING NOW

Construction of the new car parking area is almost complete. Once the bollards have been installed, the car park will be open to the public.

Construction of the new nature playspace has commenced with the removal of the old equipment and setting out of pathway locations.

We are also working on the irrigation system for the new open space area.

Photos of these areas is coming soon.

The Your Say page will continue to provide updates and opportunities to stay informed and get involved.

NATURE PLAYSPACE CONSTRUCTION UNDERWAY

It's full steam ahead for the State Government and Council funded nature playspace at the Wilfred Taylor Reserve in Morphett Vale scheduled to be open in mid-2020.

HAPPENING NOW

Construction of the new car parking area is almost complete. Once the bollards have been installed, the car park will be open to the public.

Construction of the new nature playspace has commenced with the removal of the old equipment and setting out of pathway locations.

We are also working on the irrigation system for the new open space area.

Photos of these areas is coming soon.

The Your Say page will continue to provide updates and opportunities to stay informed and get involved.

  • December Update 2019

    13 days ago
    Demolition of old playspace

    Work began with the removal of the old play equipment and constructing the new car park space and access road from Wheatsheaf Road.

    Over the Christmas and the New Year period, work ceased but has now recommenced.

    The playspace is on track to be completed by mid-2020.

    Click the December Update 2019 title to view more photos.


    Work began with the removal of the old play equipment and constructing the new car park space and access road from Wheatsheaf Road.

    Over the Christmas and the New Year period, work ceased but has now recommenced.

    The playspace is on track to be completed by mid-2020.