Site Services and Civil Upgrades

5 November 2021

We have now engaged construction contractor NEO for the delivery of the Aldinga Sports Park civil and services upgrades for all site services including the installation of mains sewer for all buildings, water and irrigation upgrades, and an electrical upgrade for the site including a larger capacity transformer.

Works also include the installation of new sports lighting for the croquet, hockey and bowls clubs, upgraded access road, new pedestrian pathways, and a new sealed car park.

Site works will commence in October 2022 and will continue until the end of 2023.

Following the relocation of the equestrian facilities to Bowering Hill Road, construction will commence on a new senior soccer pitch and a shared clubroom building for the soccer and hockey clubs.

These works are anticipated to start in March 2023 with completion of all works due by the end of 2023.