Construction is underway

2 December 2024

Work on the lighting upgrade has begun with trenches dug and conduits laid. Removal of existing light poles and installation of the new poles will occur in the week commencing 16th December 2024. There will be a break in work over the Christmas and New Year period with the asphalt and pavement reinstated in mid-January followed by installation of the new main switchboard in early February.

The project is expected to be completed by mid-February.