March 2024 update

14 March 2024

The cliff stabilisation works are progressing well. All 21 of the piles have now been drilled, had reinforcing steel installed and concrete fill poured. Each pile is 60cm in diameter and 15 metres deep!

Upcoming works include the installation of the pile cap, which consists of substantial steel reinforcing and mass poured concrete fill. Following that, the shared use path will be installed along the new alignment, with fencing and landscaping rounding out the works.

Work is on track to be completed around the end of March.