Work progressing

24 September 2025

Project update - works progressing

The refurbishment of the Noarlunga Aquatic Centre is progressing well.

Here is what has happened so far:

  • The pools have been drained.
  • Old plant room equipment has been removed.
  • Demolition work has started to prepare for new pool pipework.
  • Scaffolding has been put up so the roof and ceiling can be replaced.
  • External windows have been taken out.
  • The ceiling has been removed, and work has started on the roof.
  • Steelwork is being painted.
  • New equipment, including large water filters from overseas, have been ordered.

What is next?

  • Finish the roof and ceiling works.
  • Take down the scaffolding.
  • Start work on the new pool liner.

We are excited to see the project taking shape and will keep you updated as it moves forward.