Construction update December 2025

19 December 2025

Works are progressing and we are approximately 80% complete. The asphalt replacement has been delayed due to watermain issues and repairs.

To assist with managing the dust over the Christmas period, we have applied a dust seal to unsealed areas of the road being trafficked.

Several areas are still restricted pending completion of the water service repairs.

The asphalt works are scheduled to recommence mid-January 2026. This will be subject to watermain repairs and weather.

The remaining footpath installation, tree planting and line-marking will follow in early February 2026.

Murray Road will continue to remain under traffic restrictions until all works are complete.

We appreciate your patience while we deliver this important upgrade. We’ll continue to keep you informed as works progress.