We’re making steady progress on the Murray Road reconstruction, with around 60% of the works now complete.

So far, the team has delivered significant drainage upgrades and started preparing the ground for new footpaths. Subcontractors have also commenced work on concreting and irrigation.

Like many construction projects, we’ve encountered some design conflicts and weather delays, but crews have continued to push ahead where possible.

What’s next

  • Ongoing footpath and streetscape works
  • Continued drainage and irrigation installation
  • Final surface works

We’re currently targeting project completion in early January 2026, subject to weather and contractor availability.

Thanks for your patience while we deliver this important upgrade. We’ll continue to keep you informed as works progress.

Drainage works underway on Murray Road, with excavator and crew.

Drainage works underway on Murray Road, with excavator and crew.

Crews installing drainage upgrades along Murray Road.

Crews installing drainage upgrades along Murray Road.