Aldinga Beach Road and How Road intersection upgrade has reached a significant milestone

4 March 2025

We are pleased to provide an update on the progress of the Aldinga Beach Road and How Road intersection upgrade, which has reached a significant milestone.

Last week we achieved an important milestone with the first two layers of asphalt successfully installed.

The next milestone, currently underway, is the installation of the roundabout and associated traffic islands, with completion expected by 18 March.

Following this:

  • Final asphalt layers will be laid on 19-20 March over two consecutive night shifts—these will be the last night shifts for the project.
  • Subsequent works, including line marking, road sign installation, and landscaping, will complete the project.

Traffic Management & Community Engagement

We acknowledge recent community concerns regarding traffic impacts and delays. The current traffic management approach prioritises:

  • Safety – Ensuring a safe work environment for crews and road users.
  • Minimising congestion – Giving priority to westbound traffic to prevent queuing onto Main South Road.
  • Efficient delivery – Balancing progress with efforts to reduce disruptions.

To improve traffic flow, a stop-and-go setup was introduced on 21 February to allow eastbound traffic to resume.

Next Steps

  • Completion of roundabout and traffic islands by 18 March.
  • Final asphalt works (19-20 March night shifts).
  • Line marking, signage, and landscaping to follow.

We appreciate the community's patience and will continue to provide updates.