August construction update

15 August 2024

Section 1 - Flour Mill Road and Free Lane

All works in section 1 are now fully complete and the path is open for use.

Section 2 - Aldinga Road

The construction work between Free Lane and California Road is complete, with irrigated garden beds and trees to be installed in October/November.

Current work is focused on the section between California Road and Mainwaring Street, including the pedestrian bridge at Pethick Road.

For public safety, completed sections of the path will remain closed until the entire Aldinga Road shared-use path is complete.

Full completion of the shared use path is anticipated at the end of October 2024.