The seawall contractor, Buttrose Earthmovers, is preparing the base for the new path, coordinating this work with completion of the seawall crest. By carrying out this work early, we can streamline the construction process and bring forward the overall completion of the trail.

The City of Onkaparinga has recently appointed Neo Infrastructure, a Lonsdale-based company, to deliver the final stage of the project. This will include construction of the asphalt path, installation of fencing and solar lighting.

These works are scheduled to begin immediately after the seawall repairs are complete and are expected to take approximately six weeks.

Based on this timeline, we anticipate the full trail will be completed and open for the community to enjoy by mid-August.

Path preparation work underway